| This project was a joint venture
between ASU and the City of Mesa. Project
Engineer for water and sewer improvements
and design of approximately 5,000 feet of
8-inch, 12-inch and 16-inch water mains and
approximately 1,500 feet of 8-inch, 12-inch
and 15-inch sewer line replacement. Completed
the water and wastewater master plan designs
for the entire campus. Master planning tasks
included determining existing and future water
demands, wastewater design flows, and hydraulic
modeling and pipe sizing for water distribution
and wastewater collection systems. The master
plans also included a phased plan for converting
the existing low pressure water system to
a high pressure system. Designed master water
meters and pressure reducing stations to tie
into the existing low pressure system. Construction
Value: $30,000,000. |